B. CONSIDER APPROVAL OF A CHANGE ORDER NO. 4 SEWER MAIN RELOCATION HOLLYWOOD ROAD FROM BELL STREET TO COULTER STREET:
Overview: (Contact: Kyle Schniederjan, Director of Capital Project & Development Engineering)
Work to include relocation of a manhole, additional bore and casing, removal of abandoned utilities, and additional traffic control near Hollywood Road and Coulter Street.
Original Contract: $4,504,294.00
Previous Change Orders: $276,838.00
Current Change Order: $11,840.00
Revised Contract Total: $4,792,972.00
The change order covers additional labor and materials necessary for adjustments to the sewer line. Additional bore length and casing were required for relocation of a manhole due to a conflict with another utility. Additional concrete pavement repair and removal of an abandoned gas main were also required.
C. CONSIDER AWARD - ELECTRICAL SUPPLIES ANNUAL CONTRACT:
Overview: (Contact: Trent Davis, Purchasing Agent)
Award to Dealers Electrical Supply --- not to exceed $423,000.00
Electrical Contract awarded on Buyboard Purchasing Cooperative Contracts #527-17 and #577-18
This award is to approve a contract for the purchase of Electrical Supplies.
D. CONSIDER APPROVAL - DRAINAGE IMPROVEMENTS AT THE HILLSIDE WATER TANK WEST OF SONCY ROAD/LOOP 335:
Overview: (Contact: Roy Watts, Civil Engineer II)
1) Section 551.072 - Discuss the purchase, exchange, lease, sell, or value of real property and public discussion of such would not be in the best interests of the City's bargaining position:
A. MINUTES:
Overview: Approval of the City Council minutes for the meeting held on November 13, 2018.
B. CONSIDER APPROVAL OF A CHANGE ORDER NO. 4 SEWER MAIN RELOCATION HOLLYWOOD ROAD FROM BELL STREET TO COULTER STREET:
Overview: (Contact: Kyle Schniederjan, Director of Capital Project & Development Engineering)
Work to include relocation of a manhole, additional bore and casing, removal of abandoned utilities, and additional traffic control near Hollywood Road and Coulter Street.
Original Contract: $4,504,294.00
Previous Change Orders: $276,838.00
Current Change Order: $11,840.00
Revised Contract Total: $4,792,972.00
The change order covers additional labor and materials necessary for adjustments to the sewer line. Additional bore length and casing were required for relocation of a manhole due to a conflict with another utility. Additional concrete pavement repair and removal of an abandoned gas main were also required.
C. CONSIDER AWARD - ELECTRICAL SUPPLIES ANNUAL CONTRACT:
Overview: (Contact: Trent Davis, Purchasing Agent)
Award to Dealers Electrical Supply --- not to exceed $423,000.00
Electrical Contract awarded on Buyboard Purchasing Cooperative Contracts #527-17 and #577-18
This award is to approve a contract for the purchase of Electrical Supplies.
D. CONSIDER APPROVAL - DRAINAGE IMPROVEMENTS AT THE HILLSIDE WATER TANK WEST OF SONCY ROAD/LOOP 335:
Overview: (Contact: Roy Watts, Civil Engineer II)
1) Section 551.072 - Discuss the purchase, exchange, lease, sell, or value of real property and public discussion of such would not be in the best interests of the City's bargaining position: