A. Approval -- Change Order No. 5 - Job# 521941: 24th Pipeline 48" Well Water Transfer Line:
Original Contract: $11,740,159.00
Previous Change Orders: $1,201,862.88
Current Change Order: $(42,104.76)
For a Total of Change Orders $1,159,758.12
Current Change Order Working
Days Added: 58 Working Days
Total of Working Days Added: 187
Revised Contract: $12,899,917.12
Overview: This item approves Change Order No. 5 to the contract with Condie Construction Company, Inc. This change order consist of several additions and reductions to the contract. Including removing and adding driveways at several locations, repairs of water and sewer lines and credit for inspector overtime charges.
B. Approval -- Change Order No. 4 - Job 523005 - Replacement of WM in 45th Ave from Western St. to I-27:
Original Contract: $840,385.40
Previous Change Orders: $54,663.15 and 3 Days
Change Order No. 4: $5,800.00
For a Total of Change Orders: $60,463.15
Revised Contract: $900,848.55
Percent of Changes: 7.2%
Overview: This item approves Change Order No. 4 to the contract with Amarillo Utility Contractors. This change is for the Installation of 12" stopple during water main tie-in to keep customers in service during the tie-in from a 12" inch to 16" inch water main.
C. Approval -- Change Order No. 5 - Job 523005 - Replacement of WM in 45th Ave from Western St. to I-27:
Original Contract: $840,385.40
Previous Change Orders: $60,463.15
Change Order No. 5: $40,463.20
For a Total of Change Orders: $100,926.35
Revised Contract: $941,311.75
Percent of Changes: 12.0%
Overview: This item approves Change Order No. 5 to the contract with Amarillo Utility Contractors. This change is for adjust quantities due to field conditions.
D. Approval - Change Order No. 3 - Job # 521109: River Road Wastewater Treatment Plant Rehabilitation Project:
Original Contract: $2,638,609.00
Current Addendum: $253,606.00
Revised Contract Total: $2,995,133.00
Overview: This item is to approve Change Order No. 3 to the River Road Wastewater Treatment Plant rehabilitation project as outlined in the change order.
A. Approval -- Change Order No. 5 - Job# 521941: 24th Pipeline 48" Well Water Transfer Line:
Original Contract: $11,740,159.00
Previous Change Orders: $1,201,862.88
Current Change Order: $(42,104.76)
For a Total of Change Orders $1,159,758.12
Current Change Order Working
Days Added: 58 Working Days
Total of Working Days Added: 187
Revised Contract: $12,899,917.12
Overview: This item approves Change Order No. 5 to the contract with Condie Construction Company, Inc. This change order consist of several additions and reductions to the contract. Including removing and adding driveways at several locations, repairs of water and sewer lines and credit for inspector overtime charges.
B. Approval -- Change Order No. 4 - Job 523005 - Replacement of WM in 45th Ave from Western St. to I-27:
Original Contract: $840,385.40
Previous Change Orders: $54,663.15 and 3 Days
Change Order No. 4: $5,800.00
For a Total of Change Orders: $60,463.15
Revised Contract: $900,848.55
Percent of Changes: 7.2%
Overview: This item approves Change Order No. 4 to the contract with Amarillo Utility Contractors. This change is for the Installation of 12" stopple during water main tie-in to keep customers in service during the tie-in from a 12" inch to 16" inch water main.
C. Approval -- Change Order No. 5 - Job 523005 - Replacement of WM in 45th Ave from Western St. to I-27:
Original Contract: $840,385.40
Previous Change Orders: $60,463.15
Change Order No. 5: $40,463.20
For a Total of Change Orders: $100,926.35
Revised Contract: $941,311.75
Percent of Changes: 12.0%
Overview: This item approves Change Order No. 5 to the contract with Amarillo Utility Contractors. This change is for adjust quantities due to field conditions.
D. Approval - Change Order No. 3 - Job # 521109: River Road Wastewater Treatment Plant Rehabilitation Project:
Original Contract: $2,638,609.00
Current Addendum: $253,606.00
Revised Contract Total: $2,995,133.00
Overview: This item is to approve Change Order No. 3 to the River Road Wastewater Treatment Plant rehabilitation project as outlined in the change order.