A. Purchase - Mechanical Street Sweeper:
Heil of Texas -- $255,937.00
Overview: This item is the scheduled replacement of unit 6793, 2007 Freightliner Sweeper that has reached or exceeded useable life expectancy. Replacement approved in the 2015-2016 budgets. This award will be used by the Drainage Utility Department for daily operations. This bid represents a 6% decrease from the last purchase. Funding for this award is available in the approved FY 2015-2016 Municipal Garage Rolling Stock Budget.
B. Award - Radio Communications System Consulting and Engineering Services Contract:
AECOM Technical Services, Inc. -- $540,244.00
Overview: This item approves the consulting and engineering services contract with AECOM Technical Services, Inc. for system procurement and project implementation support of a replacement radio communications system. AECOM Technical Services, Inc. was selected as the most qualified respondent to a Request for Qualifications to provide consulting and engineering services for this project. Funding for this contract is available in the approved Management & Administration Capital Improvements budget.
C. Approval - Change Order No. 4 - Rehabilitation of Southwest 9th Avenue from Coulter Street to Amarillo Boulevard:
Original Contract: $2,061,156.95
Previous Change Orders: 111,582.20
Current Change Order: (6,068.60)
Total Change Orders: 105,513.80
Revised Contract: $2,166.670.55
Overview: This item approves Change Order No. 4 to the contract with Holmes Construction Company, L.P. for work performed on the Rehabilitation of Southwest 9th Avenue from Coulter Street to Amarillo Boulevard. The change order is for the Contractor to reimburse the City for repair work to the waterlines. No funding is required for this change order.
D. Approval - Aviation Clear Zone Easement:
Overview: Aviation Clear Zone Easement being 4,600 feet MSL above the plat of Famous Heights Addition Unit No. 43, in Section 122, Block 2, AB&M Survey, Potter County, from Philip R. Slaughter.
A. Purchase - Mechanical Street Sweeper:
Heil of Texas -- $255,937.00
Overview: This item is the scheduled replacement of unit 6793, 2007 Freightliner Sweeper that has reached or exceeded useable life expectancy. Replacement approved in the 2015-2016 budgets. This award will be used by the Drainage Utility Department for daily operations. This bid represents a 6% decrease from the last purchase. Funding for this award is available in the approved FY 2015-2016 Municipal Garage Rolling Stock Budget.
B. Award - Radio Communications System Consulting and Engineering Services Contract:
AECOM Technical Services, Inc. -- $540,244.00
Overview: This item approves the consulting and engineering services contract with AECOM Technical Services, Inc. for system procurement and project implementation support of a replacement radio communications system. AECOM Technical Services, Inc. was selected as the most qualified respondent to a Request for Qualifications to provide consulting and engineering services for this project. Funding for this contract is available in the approved Management & Administration Capital Improvements budget.
C. Approval - Change Order No. 4 - Rehabilitation of Southwest 9th Avenue from Coulter Street to Amarillo Boulevard:
Original Contract: $2,061,156.95
Previous Change Orders: 111,582.20
Current Change Order: (6,068.60)
Total Change Orders: 105,513.80
Revised Contract: $2,166.670.55
Overview: This item approves Change Order No. 4 to the contract with Holmes Construction Company, L.P. for work performed on the Rehabilitation of Southwest 9th Avenue from Coulter Street to Amarillo Boulevard. The change order is for the Contractor to reimburse the City for repair work to the waterlines. No funding is required for this change order.
D. Approval - Aviation Clear Zone Easement:
Overview: Aviation Clear Zone Easement being 4,600 feet MSL above the plat of Famous Heights Addition Unit No. 43, in Section 122, Block 2, AB&M Survey, Potter County, from Philip R. Slaughter.