A. Award - Paving of Hillside Road from Soncy Road to Helium Road:
Holmes Construction Company, L.P. -- $1,399,054.71
Overview: This item is to approve the contract for the paving of Hillside Road beginning just east of Soncy Road and extending west to Helium Road. This proposed project will consist of the widening and construction of the road surface. Funding for this project is available in the approved Capital Improvement Project Budget for the Capital Projects & Development Engineering Department.
B. Purchase - Toughbook Computer Hardware:
Award on Texas Department of Information Resources (DIR) Cooperative Purchasing Contract to Austin Ribbon and Computer Supplies, Inc. -- $78,505.02
Overview: This item approves the purchase of eighteen (18) Panasonic CF-31 Toughbook laptop computers and associated components with enhanced memory and theft management/security capabilities. These mobile, in-car computers are scheduled replacements for existing public safety units that have reached their useable lifespan. Funding for this purchase is available in the approved Information Technology public safety budget.
C. Approval -- Change Order One (1) - Job# 560020: Martin Road Lake Drainage Improvements:
Original Contract: $ 4,000,330.25
Previous Change Orders: $ 0.00
Current Change Order: $57,000.00
Total of Change Orders: $57,000.00
Revised Contract: $4,057,330.25
Overview: This item approves Change Order No. 1 to the contract with D. E. Rice Construction Company, Inc. for additional work required on the project.
D. Approval - Professional Services Agreement - Addendum #2 Engineering Services - Project #521725 Arden Road Pipeline and Pump Station Improvements:
HDR Engineering, Inc.
Overview: This item approves Addendum #2 to a June 5, 2013 Agreement for Engineering Services to perform additional engineering services to cover daily construction observation, reports and monitor compliance with the contract to meet the requirements of the Texas Water Development Board Drinking Water State Revolving Fund Loan Program (DWSRF). This addendum provides for the continuation of services by HDR, Inc. at a cost not-to-exceed $198,000.00.
E. Approval - Professional Services Agreement - Addendum #1 Engineering Services - Project #520985 Hollywood Rd WWTP Sludge Dewatering & Project #521621 Osage WTP Lagoon Solids Dewatering:
CDM Smith, Inc.
Overview: This item approves Addendum #1 to a May 20, 2014 Agreement for Engineering Services to perform additional engineering services. This addendum provides for the continuation of services by CDM Smith, Inc. at a cost not-to-exceed $10,200.00.
A. Award - Paving of Hillside Road from Soncy Road to Helium Road:
Holmes Construction Company, L.P. -- $1,399,054.71
Overview: This item is to approve the contract for the paving of Hillside Road beginning just east of Soncy Road and extending west to Helium Road. This proposed project will consist of the widening and construction of the road surface. Funding for this project is available in the approved Capital Improvement Project Budget for the Capital Projects & Development Engineering Department.
B. Purchase - Toughbook Computer Hardware:
Award on Texas Department of Information Resources (DIR) Cooperative Purchasing Contract to Austin Ribbon and Computer Supplies, Inc. -- $78,505.02
Overview: This item approves the purchase of eighteen (18) Panasonic CF-31 Toughbook laptop computers and associated components with enhanced memory and theft management/security capabilities. These mobile, in-car computers are scheduled replacements for existing public safety units that have reached their useable lifespan. Funding for this purchase is available in the approved Information Technology public safety budget.
C. Approval -- Change Order One (1) - Job# 560020: Martin Road Lake Drainage Improvements:
Original Contract: $ 4,000,330.25
Previous Change Orders: $ 0.00
Current Change Order: $57,000.00
Total of Change Orders: $57,000.00
Revised Contract: $4,057,330.25
Overview: This item approves Change Order No. 1 to the contract with D. E. Rice Construction Company, Inc. for additional work required on the project.
D. Approval - Professional Services Agreement - Addendum #2 Engineering Services - Project #521725 Arden Road Pipeline and Pump Station Improvements:
HDR Engineering, Inc.
Overview: This item approves Addendum #2 to a June 5, 2013 Agreement for Engineering Services to perform additional engineering services to cover daily construction observation, reports and monitor compliance with the contract to meet the requirements of the Texas Water Development Board Drinking Water State Revolving Fund Loan Program (DWSRF). This addendum provides for the continuation of services by HDR, Inc. at a cost not-to-exceed $198,000.00.
E. Approval - Professional Services Agreement - Addendum #1 Engineering Services - Project #520985 Hollywood Rd WWTP Sludge Dewatering & Project #521621 Osage WTP Lagoon Solids Dewatering:
CDM Smith, Inc.
Overview: This item approves Addendum #1 to a May 20, 2014 Agreement for Engineering Services to perform additional engineering services. This addendum provides for the continuation of services by CDM Smith, Inc. at a cost not-to-exceed $10,200.00.